Omni Severin Hotel 

Indianapolis, Indiana

omni-severin-hotel.jpg

Details

Occupied Hotel

Client: Omni Hotels & Resorts

A/E Consultants: C+TC Design Studio, Woodyard & Associates, Inc.

Total Guestrooms Renovated: 424 Guestrooms including 365 tub to shower conversions and HWR Replacements in Public Space & BOH. 

 

Schedule Duration:

  • 23 Weeks Total for Guestrooms 

  • 4 Weeks Total for Public Space

​

Renaissance DC Downtown Conversion to Westin DC

Washington DC

Omni Hilton Head Island Oceanfront Resort

Hilton Head Island, South Carolina

Omni Hilton Head - resort-view-studio-su

Details:

Occupied Hotel

Construction Value: $5M+

Overall SF of Project: 208KSF +

Client: Omni Hotels & Resorts

A/E Consultants: Cooper Carry Inc, J Banks Design

Total Guestrooms Renovated: 323 Guestrooms, 10 Exterior Corridors, 163 tub to shower conversions. 

 

Schedule Duration:

  • 23 Weeks Total for Guestroom Renovation

​

Omni Hiltn Head
Omni Homstead Project SL

Omni Homestead Resort

Hot Springs, Virginia

the-omni-homestead.jpg

Details:

Occupied Hotel

Construction Value: $50M+

Overall SF of Project: 1M+ 

Client: Omni Hotels & Resorts

A/E Consultants: WATG, Wimberly Interiors, Vanderweil Engineers

Total Guestrooms Renovated: 483 Guestrooms

Schedule Duration: 16 Months

Work Performed Under HITT Contracting

Positions on Project:

  • Bruce Cranford - Project Executive

  • William Shelley - Senior Project Manager

Construction Schedule:

  • Guestrooms Renovation (40) Week Phased Schedule: 

    • West Wing: 05/2022 - 02/2023

    • East Wing: 09/2022 - 02/2023

    • Tower Wing: 09/2022 - 05/2023

    • Main Building Wing: 02/2023 - 04/2023

    • Garden Wing: 03/2023 - 06/2023

  • Main Building Public Space Renovation (52) Week Phased Schedule:

    • Phase I - Phase V Public Space: 05/2022 - 08/2023

  • Garden Wing Public Space Renovation (22) week Phased Schedule:

    • 11th Floor / 9th Floor Regency Public Space: 01/2023 - 09/2023​

  • Casino Pro Shop Renovation (26) Week Schedule 02/2023 - 08/2023

  • Indoor Pool Renovation (20) Week Schedule 03/2023 - 08/2023

  • Rubino's Club House (12) Week Schedule 01/2023 - 03/2023

CY Mission Valley SL

Courtyard Marriott Mission Valley

San Diego, California

Details:

Occupied Hotel

Construction Value: $6M+

Overall SF of Project: 160K+ 

Client: Magna Hospitality

A/E Consultants: McCable Architecture Level 3 Design Group

Total Guestrooms Renovated: 321 Guestrooms

Schedule Duration: 4 Months

Work Performed Under HITT Contracting

Positions on Project:

  • Bruce Cranford - Project Executive

  • William Shelley - Senior Project Manager

​

Construction Schedule:

  • Guestroom Renovation (12) Week Schedule 10/2020 - 01/2021

  • Public Space Phased Renovation (16) Week Schedule 10/2020 - 01/2021

​

Courtyard Mission Valley.jpg
Omn LMDR SL

Omni La Mansion Del Rio

San Antonio, Texas

Omni La Mansion Del Rio.jpg

Details:

Occupied Hotel

Construction Value: $8.7M+

Overall SF of Project: 150K+ 

Client: Omni Hotels & Resorts

A/E Consultants: Omni Hotels & Resorts

Total Guestrooms Renovated: 336 Guestrooms

Schedule Duration: 8 Months

Work Performed Under HITT Contracting

Positions on Project:

  • Bruce Cranford - Project Executive

  • William Shelley - Senior Project Manager

​

Construction Schedule:

  • Guestroom Renovation (30) Week Schedule 10/2020 -01/2021

  • Guestroom Renovation & Mechanical Upgrade was executed by sections of the building consisting of (4) Phases:

  • Phase I (119) Rooms - 08/2019 - 11/2019

  • Phase II (121) Rooms - 10/2019 - 01/2020

  • Phase III (95) Rooms - 01/2020 - 03/2020

​

The Bethsdan SL

The Bethesdan Hotel

Bethesda, Maryland

the-bethesdan-hotel-tapestry (1).jpg

Details:

Occupied Hotel

Construction Value: $8M+

Overall SF of Project: 168K+ 

Client: TBC Hotels

A/E Consultants: Alliance Architecture

Total Guestrooms Renovated: 270 Guestrooms

Schedule Duration: 31 Months

Work Performed Under HITT Contracting

Positions on Project:

  • Bruce Cranford - Senior Project Manager

  • William Shelley - Project Manager

​

Construction Schedule:

  • Event Space Renovation (11) Week Schedule 01/2019 - 03/2019

  • Guestrooms Renovation (21) Week Phased Schedule  03/2019 - 08/2019

  • Exterior Façade Painting & Signage Installation (6) Week Schedule 07/2019 - 08/2019

  • 1st Floor ​Lobby & F&B Renovation (10) Week Phased Schedule 08/2019 - 10/2019

​

Hamilton SL

The Hamilton Hotel

Washington DC

Details:

Occupied Hotel

Construction Value: $4.2M+

Overall SF of Project: 31K+ 

Client: Red Hospitality Consultants

A/E Consultants: BBGM & Stonehill Taylor

Schedule Duration: 5 Months

Work Performed Under HITT Contracting

Positions on Project:

  • Bruce Cranford - Project Executive

  • William Shelley - Senior Project Manager

​

Construction Schedule:

  • Multi Phased Renovation Consisting of the Hamilton Hotel Event Space, Almas Temple Conversion to The Schuyler & The Passage Connecting the Two Buildings. 

  • Almas Meeting Room / Ballroom Conversion - 06/2020 - 11/2020

  • Almas Passage Construction - 06/2020 - 01-2020

  • Hamilton Meeting Room / Ballroom Renovation - 06/2020 - 10/2020

​

the-schuyler.jpg